Removal of fuel tanks and pipes in preparation for new construction in Ulsan

공사기간 2023.02~2024.09 발주처 Korea East-West Power

Removal of diesel storage tanks and accessory facilities at Ilsan Power Headquarters

공사기간 2022.03.07~2022.08.11 발주처 Korea East-West Power

Icheon Campus R3 Office Building Remodeling Construction_Removal

공사기간 2022.04.08~2022.12.30 발주처 SK HYENG

Demolition of the Friel Tower at the Elementary Plant

공사기간 2022.08.08~2023.01.08 발주처 Namhae Chemical

Shp jeong 2 Residential Environment Improvement Project Apartment Construction (Design) Demolition Project

공사기간 2022.08.16~2023.05.31 발주처 인천도시공사_(주)포스코건설 / Incheon City Corporation_Posco Construction

Removal of Fuel Oil Tank (R1 and R2) at Sinhonam Construction Headquarters

공사기간 2022.09.23~2022.12.09 발주처 Honam Thermal Power Headquarters, Korea East-West Power

(Emergency) Dismantling of asbestos tax at Myeonnam Elementary School

공사기간 2022.12.14~2.23.01.28 발주처 Seoul Metropolitan Office of Education Seoul Dongbu District Office of Education

(Emergency) Dismantling of asbestos tax at Myeonnam Elementary School

공사기간 2022.12.13~2023.01.30 발주처 Dongbu Office of Education, Seoul Metropolitan Office of Education

Removal of Asbestos Slate Exterior Materials for the Outer Wall of Seoul Station 2

공사기간 2022.11.14~2022.12.19 발주처 Korea Atomic Energy Research Institute

Dismantling and Removal of Asbestos from Daishin High School

공사기간 2022.07.06~2022.08.08 발주처 Seoul Metropolitan Office of Education Daishin High School

Demolition of the annex in Changseong-dong, Seoul Government Complex

공사기간 2020.11~2021.08 발주처 GOVERNMENT BUILDINGS MANAGEMENT OFFICE

Hwagok 6-1 Construction of Asbestos Removal in Public Parking Lot

공사기간 2020.12~2021.05 발주처 Gangseo-gu Seoul Metropolitan Government Office

Dismantling of Asbestos at Sincheon Elementary School in Seoul

공사기간 2020.12.15~2021.01.14 발주처 Seoul Metropolitan Office of Education

M16 Office Environment Construction (M10F, WT Remodeling) Removal_Architecture

공사기간 2021.06.18~2021.11.30 발주처 SK hyeng

Demolition and earthworks of Catholic University Incheon St. Mary's Hospital Research Building and Parking Building Extension Project

공사기간 2021.07.14~2022.06.30 발주처 CAMUS E&C

M16 Office Environment Construction Response M10F, WT Remodeling Construction_Removing

공사기간 2021.10.08~2022.01.31 발주처 SK hyeng

Demolition work of the Myeonmok Hansarang apartment and parking lot (including the dismantling of asbestos)

공사기간 2021.11.15~2022.05.13 발주처 Seoul Housing & Communities Corporation

Joongdong Middle School Removal of Asbestos Demolition

공사기간 2021.12.16~2022.01.31 발주처 Seoul Gangnam Seocho District Office Of Education In Seoul

Asbestos Demolition at Yeomkwang Women's Meditech High School

공사기간 2021.12.20~2022.01.29 발주처 Seoul Metropolitan Office of Education Yeomkwang Women's Meditech High School

Demolition during construction of the Daeyang INC plant in Geumsa-dong

공사기간 2020.04.15~2020.05.15 발주처 Daeyang INC-Wooho Construction

Reclamation Asbestos Treatment Works Among Housing Redevelopment and Maintenance Projects in Possible Living Area 1

공사기간 2020.05.15~2020.12.31 발주처 Housing Redevelopment Maintenance Business Association in Possible Living Area 1

Dismantling and Removal of Asbestos in Teacher's Building of Yangwon Elementary School

공사기간 2020.07~2020.09 발주처 SEOUL GANGSEO DISTRICT OFFICE OF EDUCATIONAL SUPPORT

Demolition Construction of Multi-Family Housing in Bojeong-dong, Yongin-si

공사기간 2020.10~2021.01 발주처 BojeongPJT

Demolition of Bangi-dong Film Hotel

공사기간 2020.11~2021.02 발주처 JS D&C

Asbestos demolition work for a kindergarten attached to Sincheon Elementary School in Seoul

공사기간 2020.12~2021.01 발주처 SEOUL GANGDONG SONGPA DISTRICT OFFICE OF EDUCATION SEOUL

Demolition work of a building, 39-1 Dosu-ri Mountain, Toechon-myeon (Executive Administration)

공사기간 2019.01.30~2019.02.13 발주처 Gl Global D&C

2019 Yeomkwang High School Asbestos Demolition (Removal) Construction

공사기간 2019.01.28~2019.02.22 발주처 Seoul Metropolitan Office of Education Yeomkwang High School

Construction of a model house during the construction of the Geumgang Pentarium C-2BL in Yangwon, Seoul

공사기간 2019.01.02~2019.01.31 발주처 KEUMKANG APT

Remodeling work of Cheongwoon Dormitory Building 5_Remodeling

공사기간 2019.02.19~2019.04.30 발주처 SK hynix-SK hyeng

Remodeling work of Cheongwoon Dormitory Building 5_Remodeling2

공사기간 2019.04.08~2019.08.31 발주처 SK hynix-SK hyeng

Demolition and Supplementation of Magnesium Smelting Plant in Gangneung Construction, Construction and Machinery Demolition Construction

공사기간 2019.07.22~2019.09.30 발주처 POSCO - POSCO E&C

Asbestos Demolition at Yeom Gwang Kindergarten

공사기간 2019.12.21~2019.12.31 발주처 Yeom Gwang Kindergarten

2019 Cheongwon High School Asbestos Demolition Project

공사기간 2019.12.26~2020.01.22 발주처 Seoul Metropolitan Office of Education Cheongwon High School

Happy Village 3rd Environmental Improvement Project_Removal

공사기간 2018.04.23~2018.12.31 발주처 SK hynix-SK hyeng

Dongducheon-Yeoncheon double-track railway No. 2 Roadbed construction and other construction of sidewalk overpass construction

공사기간 2018.06.25~2019.11.30 발주처 KOREA NATIONAL RAILWAY-POSCO E&C

Removal of asbestos and disposal of residues in the housing redevelopment and maintenance project in the woosan area

공사기간 2018.11.20~2019.11.19 발주처 Housing Redevelopment and Maintenance Business Association in woosan District

Asbestos removal and other construction works in Eunpyeong-gu (architecture)

공사기간 2018.05.23~2018.08.30 발주처 SEOUL MPA

Remodeling of the dormitory in Happy 3-dong, Cheongju_Removal

공사기간 2018.07.16~2018.12.31 발주처 SK hynix-SK hyeng

Removal of obstruction and logging works during the construction of public housing districts in yangwon

공사기간 2017.03.15~2019.12.19 발주처 KOREA LAND & HOUSING CORPORATION- KEUMKANG APT

SK Hynix boiler room for the removal of oil tank

공사기간 2017.04~2017.05 발주처 SK Hyeng

SK Hynix TC Dong 2F PKT Development Line Expansion (Removal)

공사기간 2017.05~2017.07 발주처 SK Hyeng

SK Hynix QRT Relocation and eSSD Lab Corporation_General Removal

공사기간 2017.08~2017.09 발주처 SK Hyeng

Remodeling of the Cheongdam-dong Designer Club (Removal Construction)

공사기간 2017.09~2018.06 발주처 SHINYOUNG C&D

Remodeling work of SK Hynix Happy Village 1 (formerly Gotham) (2nd demolition)

공사기간 2017.12~2018.04 발주처 SK hynix-SK hyeng

Demolition of existing buildings in Dongducheon-Yeoncheon double-track railway section 2

공사기간 2016~02~2018.06 발주처 POSCO E&C

SK Hynix Icheon Campus Cooperation Hall 1 Human Resources Removal Corporation

공사기간 2016.03~2016.07 발주처 SK ecoplant

Dismantling and demolition during the second phase of the construction of Songdo Convensia

공사기간 2016.03~2018.06 발주처 POSCO E&C

Asbestos removal and disposal of residues in the housing redevelopment maintenance project area in Gyerim District 8 in Dong-gu, Gwangju

공사기간 2016.06~2017.09 발주처 Gyerim District 8 Housing Redevelopment Association

SK Hynix Icheon Campus Cooperation Building 1 Site Construction

공사기간 2016.07~2016.08 발주처 SK ecoplant

Demolition of Hogye Jugong Model House in Anyang

공사기간 2016.10~2016.12 발주처 POSCO E&C

Demolition of the fire building at the Giheung Honsu Center in the distribution of Nonghyup Hanaro

공사기간 2016.11~2016.12 발주처 NH Development

Remodeling construction of SK Hynix Happy Village 1 (formerly Gotham) (1st demolition)

공사기간 2016.12~2017.09 발주처 SK Hyeng

Demolition of obstruction work in Poseung District, Yellow Sea Free Economic Zone (including removal of asbestos)

공사기간 2015.03~2018.03 발주처 GYEONGGI HOUSING & URBAN DEVELOPMENT CORPORATION

Asbestos Demolition Corporation of Woosung 2nd Apartment in Seocho

공사기간 2015.04~2015.07 발주처 Samsung C&T Corporation

Demolition work during the maintenance and extension of Samhwan Kamu Building

공사기간 2015.06~2016.06 발주처 CAMUS E&C

Demolition of emergency power generation room in the back of SK Hynix's welfare center

공사기간 2015.06~2015.07 발주처 SK Hyeng

Demolition work during the construction of UPS rooms on the 3rd and 1st floors of TC-dong, SK Hynix

공사기간 2015.07~2015.08 발주처 SK Hyeng

Demolition of Asbestos Tex at Yeomdong Elementary School, Seoul

공사기간 2015.12~2016.01 발주처 SEOUL GANGSEO DISTRICT OFFICE OF EDUCATIONAL SUPPORT

Provisional Construction of Measures for Natural Disaster and Prevention of Crime

공사기간 2015.03.01~2018.12.31 발주처 Geoyeo 2-1 Housing Redevelopment Maintenance Business Association

Demolition of Facilities during the construction of AmorePacific in Yongin

공사기간 2014.01~2014.12 발주처 FINE Mechanical Construction

Demolition of stone part of AmorePacific in Yongin

공사기간 2014.02~2014.03 발주처 CHEONGWOO STONE

Construction of the site of Samho District, a tourism and leisure type enterprise city in Haenam, Yeongam (Creating a golf course)

공사기간 2014.07~2014.09 발주처 서남해안레저(주)

Construction of a dormitory at the Cheongju LG site by SK Hynix

공사기간 2014.10~2014.11 발주처 SK Hyeng

Partial demolition of the main building ward during the research and accessory facility construction of the National Seoul Hospital

공사기간 2014.10~2014.11 발주처 (주)한진중공업 / HJ Shipbuilding & Construction

Seoul National University Multi-purpose Vehicle Storage Center Construction Company

공사기간 2014.10~2014.11 발주처 Yachon Housing Construction

Compensation completed housing (2nd half of the second half) demolition work in the fortress in Pungnap-dong

공사기간 2014.12~2015.02 발주처 Songpa-gu Office

Trap asbestos demolition/removal service

공사기간 2013.03.29~2013.09.30 발주처 Naval Logistics Command

Asbestos Treatment Works in the General Civil Service Office

공사기간 2013.04.15~2013.05.14 발주처 Ministry of National Defense Service Support Group

Demolition of remaining Ami Power structures

공사기간 2013.04.18~2013.07.31 발주처 SK Hyeng

Environmental facility attraction cost (designated waste disposal cost)

공사기간 2013.07.27~2013.09.07 발주처 Armed Forces Goyang Hospital

Removal of Obstacles in Seoripul Neighborhood Park (Sancheong Village)

공사기간 2013.09.23~2014.01.20 발주처 Seocho-gu Office

Demolition of AmorePacific Technology Research Institute Extension

공사기간 2013.10~2014.02 발주처 AmorePacific/Hyundai E&C

Demolition among environmental improvement works in Hyeonwoo-dong

공사기간 2013.10~2014.01 발주처 SK Hyeng

Demolition during M10A Entrance Remodeling

공사기간 2013.11~2013.12 발주처 SK Hyeng

Demolition of biodiesel gas station

공사기간 2013.11~2013.12 발주처 Seoul Metropolitan Government

Eco-Bridge Tunnel Construction Among the Dongbusan Golf & Resort Golf Course Construction Project

공사기간 2013.12~2014.01 발주처 Dongbusan Golf & ResortPFV

Demolition work during environmental improvement work at Gotham dormitory

공사기간 2013.12~2014.02 발주처 SK hyeng

Demolition of Cheongwoon Hall 6 Environmental Improvement Project

공사기간 2013.12~2014.01 발주처 SK hyeng

Construction of a new residential and commercial complex in Jangan-dong, Dongdaemun-gu

공사기간 2012.02.14~2012.04.30 발주처 CHUNGOH Construction

Grotto and dirt protection work during the expansion of Seongnam Seonggye Church

공사기간 2012.06.01~2012.12.31 발주처 BUKWANG Construction

Expansion of the Security Office of the Korea Financial Research and Training Institute and construction of a fence

공사기간 2012.03.05~2012.05.31 발주처 Hynix Engineering

Demolition of the Paris Crasang in Bundang

공사기간 2012.03.15~2012.04.15 발주처 Paris Crasang

Demolition of Park Building Construction

공사기간 2012.04.02~2012.04.11 발주처 씨티블루종합건설 / CitiBlue T&C

Designated Waste Disposal Works for Public Vehicle Gas Station

공사기간 2012.04.12~2012.06.30 발주처 Ministry of National Defense

Haeundae Udon Hotel Slab Drilling Corporation

공사기간 2012.04.17~2012.05.31 발주처 HYUNDAI DEVELOPMENT COMPANY

Demolition work during the extension of Seongnam Seonggye Church

공사기간 2012.05.01~2012.07.31 발주처 Bupyeong E&C

Construction of SKhynix Analysis Center (Removal and Waste)

공사기간 2012.05~2012.07 발주처 SK Hynix

Removal of Asbestos from the Improvement of the Roof in Yongsan Warehouse

공사기간 2012.05.30~2012.06.25 발주처 KOREA RAILROAD

Demolition of Army Power Tank

공사기간 2012.06.20~2012.08.31 발주처 SK Hynix

Demolition of new apartment building in Mangpo-dong, Yeongtong-gu, Suwon-si

공사기간 2012.07.30~2012.12.31 발주처 Hanyang Construction

Demolition of the West Gate access road

공사기간 2012.08.31~2012.10.31 발주처 Ministry of National Defense

Cooperation Building 2 Improvement of Firewalls and partitions

공사기간 2012.09.10~2012.10.30 발주처 SK Hynix

Construction of Designated Waste at Goyang Hospital for Single Accommodation

공사기간 2012.11.13~2012.12.12 발주처 The Armed Forces Medical Command

Blasting and subcontracting during the construction of the district unit project in the Suchon district of Hwaseong-si

공사기간 2012.09~2013.07 발주처 Doohyeon C&I

Sale and demolition of Garibong Public Information Center

공사기간 2011.02.28~2011.08.31 발주처 KOREA LAND & HOUSING CORPORATION

Demolition and disposal of abandoned asbestos in the housing reconstruction and maintenance project of Seocho Samik Apartment

공사기간 2011.03.03~2011.12.31 발주처 Seocho Samik Apartment Reconstruction Association

Removal of electrical equipment (transformer) from Yeongdong Thermal Power Plant

공사기간 2011.03.30~2011.06.15 발주처 Korea South-East Power 영동화력발전처

Air-conditioning Improvement for 3 Schools Other than Namsa Elementary School in Seoul

공사기간 2011.07.25~2011.09.30 발주처 DONGJAK GWANAK DISTRICT OFFICE OF EDUCATION IN SEOUL

Construction of Designated Waste Removal of Gyeongin Elementary School and 1 School in Seoul

공사기간 2011.08.04~2011.09.02 발주처 SEOUL GANGSEO DISTRICT OFFICE OF EDUCATIONAL SUPPORT

Haeundae Udon Hotel Slab Drilling Corporation

공사기간 2011.09.05~2011.09.30 발주처 Mirae contruction&industrial

Demolition of Obstacles to Additional Location of Magok Urban Development Area

공사기간 2011.12.26~2012.12.25 발주처 Seoul Housing & Communities Corporation

Asbestos removal under demolition work in Yangju New Town (Hecheon)

공사기간 2011.09 ~ 2012.06 발주처 Deokyoung Industrial Development

Demolition of temporary offices during the construction of Songdo Internationalization Complex and North Korea Residues

공사기간 2011.12~ 2012.01 발주처 KOLON E&C

Demolition and disposal of abandoned asbestos at Gangseo High School

공사기간 2011.12 ~ 2012.01 발주처 SEOUL GANGSEO DISTRICT OFFICE OF EDUCATIONAL SUPPORT

Renovation and demolition of the student hall (dormitory) of the Korea Agricultural and Fisheries University

공사기간 2011.01.11~2010.03.11 발주처 Korea National University of Agriculture and Fisheries

Renovation of the 4th and 5th floors of the Community Credit Cooperative Welfare Center

공사기간 2010.03.15~2010.03.29 발주처 Hynix Engineering

Asbestos demolition work in multi-purpose room of educational facility management office

공사기간 2010.04.16~2010.05.10 발주처 Seoul Metropolitan Office of Education

Equipment Removal Repair Work (FAB# CUB-dong)

공사기간 2010.04.13~2010.05.07 발주처 hynix

Remodeling of the main gate information room

공사기간 2010.06.28~2010.08.06 발주처 hynix

Demolition during the construction of the facility for the relocation of the Special Warfare Command/3rd Airborne Special Forces Brigade

공사기간 2010.07.05~2011.12.31 발주처 DAEWOO ENGINEERING & CONSTRUCTION

Remodeling of the guesthouse

공사기간 2010.09.01~2010.09.30 발주처 Hynix Engineering

Remodeling of the exterior wall of the central restaurant

공사기간 2010.10.10~2010.12.31 발주처 Hynix Engineering

Construction of Waste Heat Recovery System

공사기간 2010.10.22~2010.12.30 발주처 Hynix Engineering

Demolition and waste disposal of asbestos tex in a major subsidiary high school

공사기간 2010.12.13~2010.12.30 발주처 중대부속고등학교

Construction of a tourist resort in Wonam, Daemyung Resort

공사기간 2010.12.20~2011.01.10 발주처 DAEMYUNG E&C

Asbestos demolition work of Yanggang Middle School and 3 other bridges

공사기간 2010.12.27~2011.01.10 발주처 SEOUL GANGSEO DISTRICT OFFICE OF EDUCATIONAL SUPPORT

Demolition of Geumhwa Elementary School in Seoul

공사기간 2009.02.11~2009.12.30 발주처 Geumhwa learning ground guard

Demolition of Songpa Miseong Apartment

공사기간 2009.07.11~2009.07.30 발주처 Songpa Miseong Apartment

Demolition work of designated facilities in the 00 area (Gujin 5 outpost)

공사기간 2009.08.18~2009.12.20 발주처 Army 1596th Unit

Private Investment Project for Inje Military Facility Lease (D Regional Corporation)

공사기간 2009.08.19~2009.10.31 발주처 DAEMYUNG E&C

Demolition of Star Green Country Daycare Center

공사기간 2009.08.28~2009.09.16 발주처 Star Green Country Daycare Center

Gori Nuclear Power Unit 3 Peripheral Pressure Replacement Work #3

공사기간 2009.09.01~2009.11.30 발주처 HD Hyundai Heavy Industries

Construction and demolition of public parking lot in residential areas in Singil 7-dong

공사기간 2009.12.16~2010.01.30 발주처 YEONGDEUNGPO-GU

Hynix Wastewater Treatment Plant Expansion Project

공사기간 2009.12.22~2010.02.10 발주처 Hynix Engineering

Demolition of Factory Building, 26-1 Ssangam-ri, Asan-si

공사기간 2009.07 ~ 2009.10 발주처 SAMHAN E&C

Pocheon Middle School 3rd Bridge (Chusan Elementary School, Yeongjung Elementary School, Unam Elementary School) Text Removal Corporation

공사기간 2009.01 ~ 2009.03 발주처 Gyeonggido Office of Education

Asbestos removal and other construction works at six stations outside Samsong Station on the Ilsan Line

공사기간 2009.07 ~ 2009.10 발주처 KOREA RAILROAD

Removal of asbestos and other construction works at seven stations outside Beomgye Station on the Gwacheon Line

공사기간 2009.07 ~ 2009.10 발주처 KOREA RAILROAD

Demolition work during the extension of the elderly housing facility in Pyeongtaek

공사기간 2009.08 ~ 2009.09 발주처 Sungsan ENG

National Chuncheon Hospital Facilities Improvement (Machine Field) Corporation

공사기간 2009.08 ~ 2009.12 발주처 CHINHUNG E&C

Construction of Busan Anrak (3) Apartment Construction Construction Project 5 Construction of Jungji Building

공사기간 2008.01.28~2009.12.31 발주처 DAEMYUNG E&C

Demolition of the renovation of Geumhwa Elementary School in 4 schools outside Geumhwa Elementary School in Seoul

공사기간 2008.02.13~2009.09.31 발주처 TAESONG E&C

Construction of Hynix Icheon Plant's 3rd Water Purification Plant (Removal)

공사기간 2008.03.17~2008.07.10 발주처 Hynix Engineering

Removal of the main building's lamp

공사기간 2008.05.17~2008.06.16 발주처 SEOUL NATIONAL UNIVERSITY HOSPITAL

Asbestos demolition work among the Blue Gwangmyeong reconstruction works

공사기간 2008.05.30~2008.06.30 발주처 Mir E&C

Seoul National University of Education's swimming pool, rock car, and asbestos demolition work

공사기간 2008.08.01~2008.08.31 발주처 Shinsu C&E

Demolition of the new dormitory of Seoul Women's University Welfare Center

공사기간 2008.08.28~2008.08.31 발주처 Seoul Women's University

(Former) Demolition of Annex 1 and 2 of the International Cooperation Agency

공사기간 2008.10.06~2008.12.31 발주처 SEOUL NATIONAL UNIVERSITY HOSPITAL

Removal of Buildings, 400-11 Cheongcheon-dong, Bupyeong-gu

공사기간 2008.11.25~2008.11.19 발주처 Nexen tire

Gori Nuclear Power Unit 4 Peripheral Pressure Replacement Work #4

공사기간 2008.10.06~2009.02.20 발주처 HD Hyundai Heavy Industries

Namyangju Janghyeon (5) 3BL Apartment Construction 1 Tool Slate Demolition, Removal

공사기간 2007.01.09~2007.01.25 발주처 SHINIL

Demolition work during renovation of Hynix's Icheon plant M1, M2 buildings

공사기간 2007.03 ~ 200705 발주처 Hynix Engineering

MM1, 2, 3rd floor remodeling Corporation (chul construction)

공사기간 2007.03.22~2007.05.10 발주처 Hynix Engineering

M/M-dong 2nd~3rd Floor Interior Removal Construction

공사기간 2007.05 ~ 2007.06 발주처 Hynix Engineering

The dismantling and removal of asbestos slates during the construction of housing sites in Byeollae district in Namyangju

공사기간 2007.02.01~2007.12.31 발주처 KOREA LAND & HOUSING CORPORATION

Improvement/replacement of air conditioning facilities for Gori Unit 1 Construction Concrete Demolition Service

공사기간 2007.06.12~2007.07.04 발주처 K-water

Korea National Open University 1st Research and Development Corporation

공사기간 2007.08.10~2007.12.29 발주처 Korea National Open University

Icheon M10 Scrubber Room Chunghwa Slab Construction

공사기간 2007.10.19~2001.11.15 발주처 hynix

Dobong-gu Dobong-gu Bedminton Stadium, Room 84-3, Bong-dong

공사기간 2007.10.22~2007.12.27 발주처 DOBONG-GU OFFICE

Demolition work during the construction of a new waste warehouse

공사기간 2006.12.~ 2007.02 발주처 Hynix Engineering

Demolition work during the creation of Nanjido Art Creation Studio

공사기간 2006.03.01~2006.03.30  발주처 POSCO CONSTRUCTION / JEIL E&C

Demolition work during the expansion of Lotte Guri Mart

공사기간 2006.03.08~2006.05.31 발주처 LOTTE ENGINEERING & CONSTRUCTION / Sungil ENGINEERING & CONSTRUCTION

Demolition work during Hynix M10ER3 renovation

공사기간 2006.06.01~2006.07.30 발주처 HYUNDAI E&C / JEIL E&C

Demolition of temporary water supply facilities for Kori Nuclear Power

공사기간 2006.05 ~ 2006.06 발주처 HYUNDAI E&C

Demolition work during the construction of a dormitory and general education center at Seoul Women's University

공사기간 2006.11.09~2008.07.30 발주처 HYUNDAI E&C

Demolition under construction of Seongnam Lions Valley

공사기간 2006.12.~ 2007.01 발주처 Woolim E&C

Limgok Limestone Collection Tunnel Excavation Construction, Gangneung

공사기간 2005.06.20~2005.12.31 발주처 용원산업㈜

Demolition of semiconductor production facilities at Hynix's Ganam Research Institute

공사기간 2005.06.08~ 2005.08.30  발주처 TRIUS

Seoul National University Medical Research Center Demolition Project

공사기간 2005.10.01~2005.10.31  발주처 SINJIN E&C / JEIL E&C

Hynix M1, M2 Semiconductor Production Facility Demolition Corporation

공사기간 2005.12.01~2006.01.20 발주처 HYUNDAI E&C / JEIL E&C